HUNT OIL

10,000 BPD Early Production Facility

This is SPEC’s first project with Hunt Oil, signed in January 2016 and completed immediately in 2017. SPEC provided the Engineering, Procurement, Construction (EPC) and Operations & Maintenance (O&M) of 10,000 BPD very high sour oil early production facility, at the Ain Sifni block in Kurdistan, Iraq.

The services also include the following major processing equipment:

Direct fired heater
Three-phase separators (heavy and light crude)
Electrostatic Dehydrator and Desalter
H2S stripping column with nitrogen generation package

Client:
Hunt Oil Middle East Ltd.

Location:
Kurdistan, Iraq

Completion:
2017

Services:
Engineering, Procurement, Construction, Commissioning + Operations & Maintenance

Business Portfolio:
Upstream Oil & Gas